List of 2 sets of 6 ton gas steam boiler host and auxiliary equipment

2025-07-10
item number item name manufacturer name Specifications quantity unit The final destination specified in the Bid Data Sheet (project site) Arrival date (as defined by the International Chamber of Commerce Incoterms)
Earliest Arrival Date latest arrival date Bidder's arrival date [to be filled in by the bidder]
one, The main material of the process part                
1 gas steam boiler   6t, rated air supply pressure 1.0MPa, including burner, NOx<30mg/m3 2 tower   25 days after signing the contract 45 days after signing the contract  
1-1 Flue gas condenser   Supporting 6t boiler 2 tower   25 days after signing the contract 45 days after signing the contract  
1-2 Boiler supporting sound insulation cover   Supporting 6t boiler 2 set   25 days after signing the contract 45 days after signing the contract  
1-3 boiler feed pump   Supporting 6t boiler 4 tower   25 days after signing the contract 45 days after signing the contract  
1-4 Smoke cooling circulation pump   Supporting 6t boiler 2 tower   25 days after signing the contract 45 days after signing the contract  
2 Continuous Blowdown Expander   LP-0.75 1 tower   25 days after signing the contract 45 days after signing the contract  
3 Boiler Sample Cooler   Φ273 2 tower   25 days after signing the contract 45 days after signing the contract  
4 Heat exchange unit   Total heat exchange 0.28MW 1 set   25 days after signing the contract 45 days after signing the contract  
4-1 Plate heat exchanger   The heat exchange capacity of a single unit is 0.20MW, the pressure of the equipment is 1.0MPa, and a single unit bears 70% of the heat load 2 tower   25 days after signing the contract 45 days after signing the contract  
4-2 Circulating water pump for heat exchange system   Q=15m3/h, H=32mH2O P=9kW, frequency conversion 2 tower   25 days after signing the contract 45 days after signing the contract  
4-3 Make-up water pump for heat exchange system   Q=1m3/h, H=32mH2O P=0.37kW, frequency conversion 2 tower   25 days after signing the contract 45 days after signing the contract  
5 Vertical decontamination device   DN80 PN10, straight type 2 tower   25 days after signing the contract 45 days after signing the contract  
6 butterfly valve   DN80 PN16 D341H-16 4 indivual   25 days after signing the contract 45 days after signing the contract  
7 Flange check valve   DN100 PN16 H44H-16C 1 indivual   25 days after signing the contract 45 days after signing the contract  
      DN40 PN16 H44H-16C 2 indivual   25 days after signing the contract 45 days after signing the contract  
8 Flange globe valve   DN125 PN16 J41H-16C 1 indivual   25 days after signing the contract 45 days after signing the contract  
      DN100 PN16 J41H-16C 1 indivual   25 days after signing the contract 45 days after signing the contract  
      DN80 PN16 J41H-16C 3 indivual   25 days after signing the contract 45 days after signing the contract  
      DN65 PN16 J41H-16C 2 indivual   25 days after signing the contract 45 days after signing the contract  
      DN50 PN16 J41H-16C 4 indivual   25 days after signing the contract 45 days after signing the contract  
      DN40 PN16 J41H-16C 4 indivual   25 days after signing the contract 45 days after signing the contract  
      DN25 PN16 J41H-16C 3 indivual   25 days after signing the contract 45 days after signing the contract  
      DN15 PN16 J41H-16C 8 indivual   25 days after signing the contract 45 days after signing the contract  
9 head size   DN80/DN50 4 indivual   25 days after signing the contract 45 days after signing the contract  
10 steam flow meter   DN125 2 indivual   25 days after signing the contract 45 days after signing the contract  
11 cold water meter   DN25 1 indivual   25 days after signing the contract 45 days after signing the contract  
12 Industrial Bimetallic Thermometer   0-100°C 5 indivual   25 days after signing the contract 45 days after signing the contract  
13 Spring Tube Pressure Gauge   0-1.0MPa 7 indivual   25 days after signing the contract 45 days after signing the contract  
14 seamless steel pipe   ∅219×6 100 rice   25 days after signing the contract 45 days after signing the contract  
      ∅133×4 60 rice   25 days after signing the contract 45 days after signing the contract  
      ∅108×4 20 rice   25 days after signing the contract 45 days after signing the contract  
      ∅89×3.5 60 rice   25 days after signing the contract 45 days after signing the contract  
      ∅76×3.5 70 rice   25 days after signing the contract 45 days after signing the contract  
      ∅45×2.5 60 rice   25 days after signing the contract 45 days after signing the contract  
      ∅38×2.5 60 rice   25 days after signing the contract 45 days after signing the contract  
11 Steel for hangers     120 kg   25 days after signing the contract 45 days after signing the contract  
12 Aluminum silicate     3 m3   25 days after signing the contract 45 days after signing the contract  
13 0.5mm galvanized iron sheet     60 m2   25 days after signing the contract 45 days after signing the contract  
14 floor drain   DN100 3 indivual   25 days after signing the contract 45 days after signing the contract  
15 Ductile Iron Pipe   DN100 20 rice   25 days after signing the contract 45 days after signing the contract  
  Process piping installation supporting services                
1 Valve insulation   1. Insulation material: aluminum silicate
2. Insulation thickness: see design instructions for details
3. Valve specifications: see design drawings for details
0.6 m3   Complete within 10 days after arrival Completed within 30 days of arrival  
2 Flange insulation   1. Insulation material: aluminum silicate
2. Insulation thickness: see design instructions for details
3. Flange specifications: see design drawings for details
0.6 m3   Complete within 10 days after arrival Completed within 30 days of arrival  
3 Weld X-ray inspection   1. Name: X-ray flaw detection of weld seam
2. Film specification: 80mm*300mm
3. Tube wall thickness: within 16
60 open   Complete within 10 days after arrival Completed within 30 days of arrival  
4 Pipeline corrosion protection   1. Rust removal level: St3 very thorough manual and power tool rust removal
2. Brushing (spraying) type: Hongdan epoxy anti-rust paint
3. Brushing (spraying) times, paint film thickness: two times
150 m   Complete within 10 days after arrival Completed within 30 days of arrival  
5 Corrosion protection for general steel structures   1. Rust removal level: St3 very thorough manual and power tools
2. Brushing (spraying) variety: Hongdan epoxy anti-rust paint
3. Number of brushing (spraying) times, paint film thickness: see design instructions for details
100 kg   Complete within 10 days after arrival Completed within 30 days of arrival  
two, The main material of the flue gas system                
1 Double-layer insulation stainless steel chimney   DN600, height 20m 2 seat   25 days after signing the contract 45 days after signing the contract  
2 round flue   Inner diameter ∅600 δ=5mm 4 m   25 days after signing the contract 45 days after signing the contract  
3 90 elbow   DN600 R=650mm δ=5mm 2 indivual   25 days after signing the contract 45 days after signing the contract  
4 chimney muffler   DN600 2 tower   25 days after signing the contract 45 days after signing the contract  
5 Accident exhaust fan in boiler room   Low-noise DFBP35-11-6.3# explosion-proof axial flow fan, single air volume 9585m3/h 6 tower   25 days after signing the contract 45 days after signing the contract  
6 Inlet muffler for boiler room   The size is 800×630, and the maximum air volume of a single unit is 7000m3/h 6 tower   25 days after signing the contract 45 days after signing the contract  
                   
three, Fire Fighting System                
1 Hot-dip galvanized steel pipe   DN100, GB/T3091-2008, steel 240 m   25 days after signing the contract 45 days after signing the contract  
      DN65, GB/T3091-2008, steel 50 m   25 days after signing the contract 45 days after signing the contract  
2 butterfly valve   DN100, cast iron 15 indivual   25 days after signing the contract 45 days after signing the contract  
3 Low resistance backflow preventer   DN100, cast iron 2 indivual   25 days after signing the contract 45 days after signing the contract  
4 Auto exhaust valve   DN25, copper 2 indivual   25 days after signing the contract 45 days after signing the contract  
5 fire hydrant box   Single bolt type A, steel, including water gun and hose 15 set   25 days after signing the contract 45 days after signing the contract  
      For testing, steel, including water gun, hose, fire button, pressure gauge 1 set   25 days after signing the contract 45 days after signing the contract  
  Fire pipe installation supporting services                
1 Pipe oiling   1. Rust removal level: St2 Thorough manual and power tool rust removal
2. Paint type: anti-rust paint
3. Number of times of brushing, paint film thickness: see design instructions for details
240 m   Complete within 10 days after arrival Completed within 30 days of arrival  
6 ton, gas steam boiler host,auxiliary equipment

4 ton gas fired steam boiler manufacturer

2026-08-12

XHJ is an national fixed-point of the first level of provinces of boiler,pressure vessel manufacture enterprise and one of the the biggest and the earliest of fuel and gas boiler manufacture enterprise in China. The company take the manufacture of boiler,pressure vessel as the foundation, established of the industrial system in product development

Horizontal 3 Pass Wet Back Boiler Factory

2026-07-31

XHJ boiler is very popular in global boiler market, many factory choose our boiler for stable performance. WNS series boiler is well known as a horizontal style three pass wet back boiler.This type boiler used widely in industries and can be designed as steam boiler or hot water boiler according customer inquiry.

How to Calculate Gas Boiler Burners Fuel Consumption?

2026-07-30

If you use gas boiler for heating, choosing good quality burner is very important. XHJ boiler always focus on high efficiency burner production, help user save more gas cost in daily use. Gas boiler burners consume fuel based on their BTU output. Natural and propane gas have specific levels of energy contained within them. One cubic-foot of natural gas contains 1075 BTUs of energy

2TPH gas fired ASME certified boiler factory

2026-07-24

XHJ Boiler Company,boiler manufacturer with A class license and ASME certification in china.So we can supply 2TPH gas fired ASME certified boiler include:single drum WNS series 2TPH gas fired ASME certified boiler and double drum SZS series 2TPH gas fired ASME certified boiler.

How to Select Natural Gas Boiler

2026-07-23

Natural gas boilers are widely used in industries such as food processing, chemicals, pharmaceuticals, hospitals, hotels, and district heating. Choosing the right boiler model not only affects production efficiency but also directly impacts investment costs and operating expenses.

Item-by-item quotation for the complete set of equipment for the coal mine's 4-ton gas hot water bo

2025-11-02

Coal mines are mainly coal-producing mines. There is no shortage of coal in every coal mining area, so most coal mines use coal-fired boilers. However, becau

The quotation of 10 tons oil and gas steam boiler includes installation fee

2025-10-30

WNS10-1.25-Y and Q are 10-ton oil-fired gas-fired steam boilers with a pressure of 1.25MPa. This boiler adopts the current popular horizontal internal combus

Operating costs and quotations of gas steam boilers for soy sauce production

2025-10-23

Soy sauce is a traditional Chinese condiment, which evolved from soy sauce. As early as more than 3,000 years ago, there was a record of making soy sauce in

14000kw gas hot water boiler, asme certified

2025-10-12

Recently, a customer called to inquire about a 14,000kw gas hot water boiler, which requires ASME certification and is exported to Spain. The 14000kw gas hot

20 tons of fuel gas boiler PLC control cabinet configuration list

2025-10-07

20 tons of fuel gas boiler PLC control cabinet configuration list serial number category Device name Sp

Get An Instant Quotation

For all inquiries, please fill in the form below (* are required) to send us a brief message, and we will get back to you as soon as possible.


  • Heat Converters
  • Pressure Converters
  • Temperature Converters

Any question, please contact us for free. Phone number: +86-371-86167233 Whatsapp: +86 177 19888549 Email:[email protected]

KW
bar
    °C